Licensing Schedule
The FERC licensing schedule requirements are shown in the table below and depict milestones in the Project licensing process.
Milestone Activity |
Timeframe |
| Preliminary Permit Issued | October 2004 |
| PAD/NOI | August 2007 |
| Initial Consultation Meeting | September 2007 |
| Second Preliminary Permit Issued | February 2008 |
| Study Planning and Field Studies | September 2008 - September 2010 |
| Scoping Process | May - August 2009 |
| Submit Draft License Application | August 2010 |
| Submit Final License Application | January 2011 |
| FERC Order Issuing New License | August 2011 |