Milestone Activity
Timeframe
Preliminary Permit Issued October 2004
PAD/NOI August 2007
Initial Consultation Meeting September 2007
Second Preliminary Permit Issued February 2008
Study Planning and Field Studies September 2008 - September 2010
Scoping Process May - August 2009
Submit Draft License Application August 2010
Submit Final License Application January 2011
FERC Order Issuing New License August 2011